b. Weaving the braided wire evenly around the process as required.
c Install the runner on the knitting machine, and pull the braided wire head out of the hole.
d According to the length of the product requires a good take-up reel.
e Select the pitch gear according to the process requirements.
f Check whether the quality of the product in line with the production requirements.
2. Drive a. Pass the braided core through the lead hole of the braider.
b Start the machine and introduce the core from the lead hole to the take-up reel.
Third, in the process of driving a check runner lubrication, to prevent jumps.
b Weaving density does not match to increase or decrease the number of monofilaments.
c check the burr, too large should be repaired.
Fourth, parking a turn off the power.
b Wrap the braided cable end.
c Fill out the records, label the process card, and specify the model specifications, length, process name, operator and date.
d Send the scrap copper wire to the designated place.
Fifth, the quality requirements a knitted wire on the car should be smooth, no oil, bumps, oxidation and other phenomena.
b The braiding layer is not allowed to be connected continuously. The exposed threads should be trimmed. The length of the replacement ingot should not be less than 1 meter.
The c braid has no hole mark, uniform pitch, and neat rows.
Weaving machine operating procedures
Knitting Machine Operation Procedures 1. Preparation before Driving a Check the power supply and the operation of various parts of the machine, and add lubricant to each operation site.